Week13 - Break, Midterm review
Writing on '2025.4.23' for recording the review.
What should I achieve in this week:
- On your final project site post a system diagram for your project,
- List the tasks to be completed,
- Make a schedule for doing them,
- Meet with your local and global instructors
- To review these and your weekly assignments.
Review my weekly assignments.
Until 23rd April, 2025, I have finished 12 weeks assignment. And I just finished CNC machine with my classmates.
And I have some final's works that need to be finished.
Post a system diagram for my final project
Refer to my final project page - System Design (Electronics), I designed the system of my final project. It's a sensors connected to a Microcontroller and send the sensing data to other microcontroller.
There're many sensors need to be bought:
- GNSS Antennia
- HX711 load cell sensor
- WWZMDiB 12 Water Level sensor
- HC-SR501 PIR Sensor.
After mid-term review with my global Instructor, I need to plan my time schdule to manage my project progress. I already got GNSS Antennia and the essential MicroController which are used for finishing my week11 assignment. HX711, WWZMDBiB 12 and HC-SR501 will be bought soon.
List the tasks to be completed
Weekly Assignment
There are 7 weeks left to finish the weekly assignment and I have finished 12 week assignments. Just keep going and catch up the progress.
Final Project
In my final project, there are so much knowledge needed to apply for my final project: Here's the techniques which I have studied in Fab Academy will apply to Final Project
- Layout the cat house - Week 7 - CNC milling
- Design and Produce the PCB - Week 6 & 8 Electronic design & product
- Sensors testing - Week 9 - Input Devices
- Data Transfer and web server - Week 11 - Network & Communication
- Auto Feed - Week 10 - Output Device and Week 12 - Machine Design
More technique will be applied in future studies.
- User Interface - Week 15 Interface and Application Programming
Finished tasks:
- Layout the cat shelter for final project in week7 assignment
- Testing the GNSS Antennia in week9 assignment
- Built a web server and transfer the sensing data in week 11 assignment
Future tasks
- Buying the sensors HX711, WWZMDiB and HC-SR501 and test
- 3D modeling and printing the food bowls and water bowls for placing in the cat shelter
- Create the user interface to show the sensing data from the cat shelter
- Make a simple auto feeder to feed the stray cats automatically
Make a schedule for doing the tasks
It will be recorded in my final project pages.
A Gantt chart is added in notion in the following link:
Meeting with local & global instructors
A zoom meeting is finished in Beijing time 17:00, 23rd April, 2025.