13. Molding and Casting¶
Schedule - Next week¶
interface and application programming
individual assignment:
• write an application that interfaces a user with an
input &/or output device that you madegroup assignment:
• compare as many tool options as possible
Date:
- Apr 29 (Wed)
- Apr 30 (Thu)
- May 1 (Fri)
Schedule - Last half semester¶
Apr 22: molding and casting
Apr 29: interface and application programming
May 06: system integration
May 13: wildcard week
May 20: applications and implications, project development
May 27: invention, intellectual property, and income
Jun 08-12: final project presentations
Assignment¶
Group Assignment¶
Group assignment - mechanical design
- review the safety data sheets for each of your molding and casting materials,
then make and compare test casts with each of them - compare mold making processes
Tip: Molding and Casting Materials/Tools/Machines/Designs/Safety_FA25
Materials
- Machinable wax
- Ferris File-A-Wax : blue
- Size: 13cm? x 18cm? x 2cm ?(Re-use)
- Surfacing
- Tips: cast wax
Machines
- Genmitsu Cubiko
- Work Area: 150mm x 110mm x 40mm
Individual Assignment¶
Individual Assignment
- design a mold around the process you’ll be using,
produce it with a smooth surface finish that
does not show the production process toolpath,
and use it to cast parts - extra credit: use more then two mold parts