Mid Term

Mid Term Review

Documentation update — 21 October 2026

I have a proposed system diagram and remaining-work sequence. I still need to record the local/global instructor review: date, participants, feedback and agreed next actions. The earlier meeting paragraph was not supported by a dated record in this archive.

Assignment

Post a system diagram for my final project, list the tasks to be completed, make a schedule for doing them, and meet my local and global instructors to review these and my weekly assignments.

System diagram

This is my proposed architecture; the final fitted parts still need verification. It shows how I intend to connect the solar panel and battery for power, the XIAO microcontroller in the middle, the GPS module and the compass as inputs, and the E-Ink display as the output.

Inputs
GPS moduleu-blox Neo-M8N
CompassQMC5883
→
Controller
XIAO ESP32-C6reads inputs, computes heading & distance
↑
Solar panel + Battery / MPPTpower supply
→
Output
E-Ink display2.7" route & direction

Proposed TrailNAV system diagram: GPS and compass would feed the XIAO ESP32-C6, which is powered by the solar panel and battery and drives the E-Ink display.

Tasks and schedule

An honest list of where each part of TrailNAV stands and when I plan to finish it.

OrderPlanned workEvidence needed to move on
1 — inventoryConfirm controller, GPS, screen, battery and charging circuit; reconcile the BOM.Part labels, receipts and power/interface requirements.
2 — electronicsIdentify/design and fabricate the final PCB; recover editable sources.Schematic, PCB, fabrication record and board test.
3 — firmwareRead GPS/compass, implement waypoint storage and drive the actual display.Uploaded source versions and observed outputs.
4 — integrationMount the electronics and battery; route and secure the wires.CAD, internal photos and an assembled-device test.
5 — validationRun the navigation, charging and runtime tests.Measured results against the test plan.
6 — presentationUpdate the slide/video with actual functionality and review the archive with my instructor.Final source files, working demonstration and review feedback.

This is my proposed order of work, not a record of completed sessions. I still need to agree calendar dates and lab access with my instructor; I have not backdated a schedule to the original course weeks.

Meeting my instructors

I need to arrange or document the actual review with my local and global instructors. I will record the date, who attended, which weekly gaps were discussed, and the agreed project scope and schedule. I have not treated the draft system diagram as evidence that this meeting took place.

Review record pending: dated feedback and agreed actions. A photograph can support the record, but is not a substitute for it.