What tasks have been completed, and what tasks remain?

Tasks

Status

2D and 3D design.

Completed

Electronic Design and Production

Completed

Embedded microcontroller interfacing and programming

Completed

System integration and packaging

90% Completed

Additive fabrication processes

Completed

Subtractive fabrication processes

Completed

what tasks have been completed, and what tasks remain?

All components of this project are completed. All that remains is the manual assemble and actual program measurement calibrations that can only be done when assembled.

what's working? what's not?

All individual components have been tested and working.

what questions need to be resolved?

No major questions need to be resolved at this time.

what have you learned?

The major thing that I have learnt is that time management is the key to a successful project. With respect to this project, precise measurements was key factor and always do a sketch.