Midterm Review
On your final project site post a system diagram for your project, list the tasks to be completed, make a schedule for doing them, meet with your local and global instructors to review these and your weekly assignments
Tasks & Schedule
Week | Tasks | Priority | Remarks |
---|---|---|---|
Week1-week4 | Finalise the topic of final project and discussed the idea with Instructor | High | Completed |
Week5-Week8 | Developed first cartoon prototype, listed all materials that are required for final project and sketched the flow chart for final project. | High | Completed |
Week9-Week11 | Worked on the input and output devices for the final project and also developed second prototype using cartoon. | High | Completed |
Week13-Week14 | Designing the chocolate dispenser, 3d printing and testing it with chocolates | High | On going |
Week14-week15 | Designing the main body of model using low poly 3d model in fusion 360 and also cutting the model using zund and assembling them | High | Not started |
Week15-Week16 | Compiling all the codes that are needed for programing,debugging and also making new board for the project if required. | High | On going |
Week16-Week17 | Attaching the electronics parts with the main body and testing with children. | High | Not started |
Week17-Week18 | Finalising design for the final project and working fully on it. | High | Not started |
Week18 till end | Prepare documentation and presentation materials(poster and video). | High | Not started |
Task and Schedule for Final Project
Starting from the second week of May, I will be giving full priority to whatever left over task are there for my final project in order to sucessfully complete the project and to do fruitful presentation of my project.
Date | Tasks | Priority | Remarks |
---|---|---|---|
6/05 - 8/05 | Need to design the new circuit board for my final project and do milling of the board | High | On going |
6/05 - 8/05 | Design the low poly model of dog using fusion 360, use paperkura software to unfold it and cut using zund | High | Not started |
9/05 - 11/05 | Need to do integration with all components by programming | High | Not started |