Project Development¶
Tracking my project progress:
what tasks have been completed, and what tasks remain?
- I am done testing individual functionalities for the project and intergration of RFID as INPUT and Solenoid as OUTPUT.
-
I still need to make my final board and intergrate MP3 player and Neo Pixles
-
As for the design, everthing is ready but still need to decide on the color of my casing.
what’s working? what’s not?
-
RFID and solenoid is working and it pops braille pattern.
-
Casing looks perfect, but might have to make few design changes. I am having a difficult time intergrating DF mini player to play sound. Also I need to intergrate buck convertor and 12-5 volts regulator is over heating.
what questions need to be resolved?
-
What color to choose for my casing. Is the braille cell poping to the height requires. How to give power supply from battery for future?
-
Script for my video and I want to test my project with someone visually impared.
what will happen when?
25th May: Design my board with buck convertor
26th- 28th May: Testing of my board and also prallelly design my final print
29th May-30th May: Final assembly and Testing
31st May: Decide of Script
1st June: Decide on the script and shoot video
2nd -3rd June : Make video and Slide
4th June: Finish Documentation. Upload slide and presentation.
5th June: Presentation day.
what have you learned?
-
Most importantly, the time management when in the final week to the presentation.
-
What worked for others won’t work for you.
-
When there are three different power supply requirements bevery careful not to supply higher voltage lower voltage equipment.