Mid Term Review¶
Assignment:
- On your final project site post a system diagram for your project, list the tasks to be completed, make a schedule for doing them, and meet with your local instructor to review these.
Tasks & Schedule¶
Week | Tasks | Priority | Remarks |
---|---|---|---|
Week 1-8 | Evaluate package design and finalize specifications for the next iteration. Test the first iteration final board’s functionality and performance. | High | Completed |
Week 9 | Research and determine the required output voltage for the speakers. Begin integration of camera module into xiao ESP32 S3 board. | High | Completed |
Week 12-13 | Test ultrasonic sensors and integrate LED indicators. Develop code for capturing images triggered by presence detection. Integrate camera module and test functionality. | High | Completed |
Week 14-15 | Implement networking protocols for transmitting captured images to App. | High | Ongoing |
May 10, 2024 | Finalize first prototype by May 6th. | High | Ongoing |
Week 16-17 | Establish connection protocols, integrat with indoor doorbell system and test functionality. | Medium | Not begun |
Week 18 | Prepare documentation and presentation materials. | High | Ongoing |
- | Research solenoidal lock mechanisms and select suitable one. Design and prototype solenoidal lock system. | Medium | - |
If there’s sufficient time available, I’ll proceed with developing the medium priority tasks once I’ve completed the high priority tasks.