This poses us a few question that have to be answered so we could keep the track of the progress, but the value of the questions changes as the days progress hence refering the date the current of the updation of the page, following we could conclude as the progress of the project.
Currently the deadline set is to get the project completed before the project presentations, for which the alloted slot for me is on 15th of june.
But considering a few moments of buffer time, the date I am considering is to be 14th of june.
Hence looking today as 10th of june, I have 4 days to get my task done.
For the current situation the assembly of the project has been done, along with the electronic components, the boards have been manufactured, and all the components have been tested.
Things actually had to be planned using a gant chart as seen here..
Considerably the only task left is to program the board and get it in action, along with compiling the video and slide.
For this I am quite sure that it would be completed in the due time.
Till date I have been able to make the machine stand, program the board with basic programs to test it's working.
Also all of the electronic components have been tested individually including the motors, vaulves, relays, and drivers.
The only thing to be upgraded in the machine is to upload the a actual program that would give out the bhel, and that has been under working progress and would be completed in due time.
This project along with the process has been a great learing adventure where I was able to work with a lot of things that would be unsed in the future challenges to come.
Following listed are few of the things I learnt significantly:-